據(jù)NS ENERGY 5月18日消息,雪佛龍和道達(dá)爾能源已經(jīng)批準(zhǔn)了位于美國墨西哥灣深水區(qū)的Ballymore項(xiàng)目,該項(xiàng)目將涉及約16億美元的投資。
該油田于2018年發(fā)現(xiàn),將通過鉆探三個(gè)生產(chǎn)井進(jìn)行開發(fā)。這些將通過一條4.8公里長的出油管線與現(xiàn)有的雪佛龍運(yùn)營的Blind Faith平臺相連。
Ballymore項(xiàng)目的第一批石油預(yù)計(jì)將于2025年開采。
據(jù)雪佛龍稱,該項(xiàng)目生產(chǎn)的石油和天然氣將利用現(xiàn)有基礎(chǔ)設(shè)施進(jìn)行運(yùn)輸。道達(dá)爾能源表示,這將確保降低開發(fā)成本和排放強(qiáng)度。
雪佛龍北美勘探和生產(chǎn)總裁Steve Green說:“雪佛龍?jiān)诿绹鞲鐬车纳a(chǎn)是我們投資組合中碳強(qiáng)度最低的生產(chǎn)之一,約為6千克二氧化碳當(dāng)量/桶油當(dāng)量,是全球行業(yè)平均水平的很小比例。”
“一旦完工,預(yù)計(jì)Ballymore將增加美國生產(chǎn)的能源的可靠供應(yīng),以幫助滿足全球需求。該項(xiàng)目旨在通過使用海底回接方法、標(biāo)準(zhǔn)化設(shè)備和可重復(fù)的工程解決方案來降低開發(fā)成本——利用現(xiàn)有的運(yùn)營基礎(chǔ)設(shè)施。”
Ballymore標(biāo)志著雪佛龍?jiān)诿绹鞲鐬砃orphlet區(qū)塊中的首次開發(fā)。
該油田位于密西西比峽谷地區(qū),水深約6600英尺,距離新奧爾良東南部約260公里。
雪佛龍公司表示,可以從該油田開采超過1.5億桶石油當(dāng)量資源。
通過其子公司雪佛龍美國公司,該公司擁有Ballymore項(xiàng)目60%的運(yùn)營股權(quán)。道達(dá)爾能源通過其子公司TotalEnergies E&P USA持有剩余40%的股份。
道達(dá)爾能源美洲勘探和生產(chǎn)高級副總裁David Mendelson說:“在發(fā)現(xiàn)Ballymore油田僅四年后,就批準(zhǔn)了該油田的開發(fā),這是我們在墨西哥灣勘探努力的結(jié)果。”
“由于其循環(huán)發(fā)展理念,這一決定符合我們專注于低盈虧平衡和低排放石油項(xiàng)目的戰(zhàn)略。”
祝精燕 摘譯自 NS ENERGY
原文如下:
Chevron, TotalEnergies sanction $1.6bn Ballymore project in US Gulf of Mexico
Chevron and TotalEnergies have sanctioned the Ballymore project in the deepwater US Gulf of Mexico, which will involve an investment of around $1.6bn.
Discovered in 2018, the field will be developed by drilling three production wells. These will be tied back to the existing Chevron-operated Blind Faith platform through a 4.8km long flowline.
First oil from the Ballymore project is expected to be drawn in 2025.
According to Chevron, oil and natural gas produced from the project will be transported by using the existing infrastructure. This will ensure lesser development costs and lower emission intensity, said TotalEnergies.
Chevron North America exploration and production president Steve Green said: “Chevron’s U.S. Gulf of Mexico production is some of the lowest carbon intensity production in our portfolio at around 6 kg CO2 equivalent per barrel of oil equivalent and is a fraction of the global industry average.
“once complete, Ballymore is expected to add a reliable supply of U.S. produced energy to help meet global demand. The project is designed to lower development costs by using a subsea tieback approach, standardised equipment and repeatable engineering solutions – leveraging existing operated infrastructure.”
Ballymore marks the maiden development for Chevron in the Norphlet trend of the US Gulf of Mexico.
The field is located in the Mississippi Canyon area in a water depth of around 6,600ft, and nearly 260km southeast of New Orleans.
Chevron stated that more than 150 million barrels of oil-equivalent resources can be potentially recovered from the Ballymore field.
Through its subsidiary Chevron U.S.A., the company has an operating stake of 60% in the Ballymore project. TotalEnergies holds the remaining 40% stake through its subsidiary TotalEnergies E&P USA.
TotalEnergies exploration and production senior vice president Americas David Mendelson said: “Sanctioning the Ballymore field development, only four years after the discovery, is the result of our exploration efforts in the Gulf of Mexico.
“Thanks to its tie-back development concept, this decision fits TotalEnergies’ strategy of focusing on oil projects with low breakeven and low emissions.”
免責(zé)聲明:本網(wǎng)轉(zhuǎn)載自其它媒體的文章及圖片,目的在于弘揚(yáng)石化精神,傳遞更多石化信息,宣傳國家石化產(chǎn)業(yè)政策,展示國家石化產(chǎn)業(yè)形象,參與國際石化產(chǎn)業(yè)輿論競爭,提高國際石化產(chǎn)業(yè)話語權(quán),并不代表本網(wǎng)贊同其觀點(diǎn)和對其真實(shí)性負(fù)責(zé),在此我們謹(jǐn)向原作者和原媒體致以崇高敬意。如果您認(rèn)為本站文章及圖片侵犯了您的版權(quán),請與我們聯(lián)系,我們將第一時(shí)間刪除。